Civil Engineering Billing Guide: BOQ Preparation & Estimation
📘 Module 5 of 7 – Finishing Works (Quantity Estimation)

Civil Engineering Billing Guide: BOQ Preparation Step by Step and Quantity Estimation from Drawing

Advance your proficiency in construction field documentation with this practical guide. Master structural material computations and assemble verifiable, real-world Bills of Quantities (BOQ) for plastering, structural tiling, premium painting layouts, and custom stone counter surfaces based on verified G+1 engineering blueprints (23′-0″ × 36′-6″).

Ground Floor Architectural Drawing - G+1 Residential Building 23'x36.5'
📐 Ground Floor Plan Reference – All room dimensions & openings derived from this drawing
📏 IS 1200 Compliant 📊 DSR Reference 🏗️ Real Site Data

📖 Essential Site Glossary (Short Reference)

PerimeterTotal linear length of all walls in a room.
DeductionVoid area (doors/windows) subtracted from gross wall area.
Dado TilingVertical wall tiles in wet areas & kitchen backsplash.
Skirting100mm high tile strip at wall base.
NosingPolished front edge of a granite countertop.
IS 1200Indian Standard measurement code for civil works.

📍 1. Structural Flooring Optimization & Plan Room Analysis

📋 Ground Floor Extracted Areas

RoomDimensions (ft)Area (m²)Finish
Drawing Hall11’6″ x 17’3″18.43Premium Vitrified
Kitchen/Dining9’6″ x 15’6″13.68Anti-skid
Bed Room10’0″ x 12’6″11.61Vitrified
Store Room9’9″ x 5’0″4.53Ceramic
Bath + WCCombined3.90Anti-skid
Passage3’6″ x 9’6″3.09Vitrified
💡 Pro tip: Add 5% cutting wastage for procurement.

🧮 Calculation Method (m²)

📐 Flooring Area = Internal Length (m) × Internal Width (m)
⚡ Example: Living Room
11’6″ = 3.505 m  |  17’3″ = 5.258 m
→ 3.505 × 5.258 = 18.43 m²
Bed Room: 10’0″ (3.05 m) × 12’6″ (3.81 m) = 11.61 m²
✅ Always measure from internal wall faces. Do not add skirting area here.

🧱 2. Linear Skirting Rules & Vertical Dado Configurations

📋 Skirting & Dado Reference Quantities

Location / ItemPerimeter/Length (m)Door DeductionNet QtyUnit
Bed Room Skirting13.720.9112.81m
Drawing Hall Skirting18.501.0717.43m
Bath Dado (Full)6.7114.29
Kitchen Dado (backsplash)3.50 (L)2.14
🧹 Skirting protects walls – billed in metres (m). Dado in m².

📐 Calculation Steps

📏 Skirting (m) = 2×(L+W) – Σ(Door widths)
Bed Room skirting:
L=3.05m, W=3.81m → Perimeter = 13.72m
Door width = 0.91m → Net = 13.72 – 0.91 = 12.81 m
🧼 Dado Area (m²) = Tiled wall length × Height
Bathroom dado: Perimeter 6.71m × 2.13m height = 14.29 m²
Kitchen backsplash: Counter length 3.5m × 0.61m = 2.14 m²

🚪 3. Openings Deduction Logic for Plastering and Painting Work

📋 Structural Openings Schedule

OpeningSize (m)Area (m²)QtyTotal Deduction
Main Door (D)1.07×2.212.3612.36
Drawing Hall Window1.37×1.522.0812.08
Bed Door (D1)0.91×2.212.0112.01
Kitchen Door (D2)0.91×2.212.0112.01
Bed Window (W3)1.37×1.221.6723.34
❗ Openings 0.5–3 m²: deduct full face (IS 1200). Saves ~23.84 m² on GF.

🧮 Net Plaster Calculation

Net Plaster = (Perimeter × Height) – Sum of openings (0.5–3 m²)
Bed Room Example:
Gross wall = 13.72m × 3.05m = 41.85 m²
Deductions = Door(2.01) + Window1(1.67) + Window2(1.67) = 5.35 m²
Net Plaster = 41.85 – 5.35 = 38.17 m²
✅ Same area used for wall painting & putty. Never skip deductions.

🍳 4. Dual-Unit Calculations for Polished Granite Countertops

📋 Kitchen Platform (GF Example)

DescriptionLength (m)Width (m)QuantityUnit
Granite platform top3.660.612.23
Polished nosing (bullnose)3.663.66m
🔧 L-shaped: (L1×0.61)+(L2×0.61) ; Nosing = L1+L2

📏 Calculation Method

🧾 Top Area (m²) = Platform Length × 0.61 m (2ft depth)
✨ Nosing (m) = Total exposed edge length
🔪 Example (Straight run):
Length = 3.66 m → Top area = 3.66 × 0.61 = 2.23 m²
Nosing length = 3.66 metres
⚠️ Nosing is a separate DSR item – often missed in BOQ. Sink cutout deduction only if >0.1 m².

📋 Comprehensive Wall Plaster & Paint Measurement Sheet

Room / ZoneGross Wall (m²)Deduction (m²)Net Plaster (m²)Ceiling (m²)
Drawing Hall78.508.9069.6018.43
Kitchen/Dining62.406.4555.9513.68
Bed Room41.853.6838.1711.61
Bath + WC (Base)28.402.2426.163.90
Store Room25.302.5722.734.53
Passage24.600.0024.603.09
TOTAL (GF)~261.05~23.84~237.2155.24
First-floor footprint mirrors ground floor; quantities doubled for G+1 total except kitchen platform.

📊 Final BOQ Abstract: Finishing Works (G+1 Project) of Ground floor

Item DescriptionTotal Qty (Ground Floor)Rate (₹)Total Cost (₹)
Internal Wall Plastering (Excluding wet area walls)211.05 m²13528,491.75
Vitrified Tile Flooring (Bed, Hall, Kitchen, Store, Passage)51.34 m²45023,103.00
Dado Tiling (Bath + WC full height walls)24.02 m²52012,490.40
Acrylic Emulsion Wall Painting211.05 m²428,864.10
Wall Putty + Primer Application Base211.05 m²388,019.90
Ceiling Plastering Work55.24 m²955,247.80
Premium Granite Flooring (Balconies / Otla)6.69 m²7505,017.50
Skirting Tiling Work (Bed, Hall, Store)39.13 m853,326.05
Ceiling Painting Work55.24 m²281,546.72
Anti-Skid Floor Tiling (Bath + WC)3.90 m²3801,482.00
Kitchen Dado Tiling (Counter Backsplash)2.14 m²5201,112.80
Granite Kitchen Platform Top2.23 m²1,8504,125.50
Polished Front Edge Nosing3.66 m175640.50
💰 GRAND TOTAL (Ground Floor)₹1,03,468.52
Rates illustrative (DSR). GST extra. First floor identical layout (add same value for G+1 total).

📌 Quick Reference Cheat Sheet

  • Flooring (m²): Length × Width
  • Skirting (m): (2 × [L+W]) – Σ(Door openings)
  • Net Plaster (m²): (Perimeter × Height) – Openings schedule (0.5–3 m² full deduction)
  • Kitchen Top (m²): Length × 0.61 m
  • Nosing (m): Countertop edge length
CE

About The Author

Prepared by a Senior Civil Engineering Professional with over 15+ years of active industry experience in real estate infrastructure estimation, structural contract billing management, Bar Bending Schedules (BBS), and precision field quantity surveying.

❓ Technical Frequently Asked Questions

1. What baseline standard governs open area volume deductions for finishing works?

Per Indian Standard IS 1200 parameters, architectural window and entry openings measuring between 0.5 and 3.0 square meters require full individual structural face reductions across internal wall surface calculations to minimize inventory tracking variance.

2. Why are base tile flooring and wall border skirting evaluated using independent metric indicators?

Flooring covers internal horizontal space dimensions evaluated by overall area footprint (m²). Wall perimeter base border masking (skirting) operates lineally (meters) and functions separately to exclude intersecting wall openings from physical cost aggregates.

3. How should stone platform edge finishing be handled to maintain billing compliance?

Slab surface counters are initially tallied using localized area limits (m²). The exposed perimeter face requires distinct manually-intensive polishing edge-work (nosing), requiring separate linear item tracking classifications under primary DSR schedules.

4. What design configuration serves as the dimension baseline for residential counter estimates?

Standard engineering practices standardize integrated counter installations to a fixed width alignment coefficient of 0.61 meters (2 feet), enabling accurate face length multiplications during planning phases.

5. How do you scale multi-tier property costs reliably from ground-level calculation metrics?

For matching overhead construction tiers, individual room finishing metrics can be scaled exponentially across shared levels. Fixed specialized non-repeating layouts—including localized ground culinary countertops—are accounted for separately within the abstract matrix.